£3.5bn Plan To Improve Congested Rail Network

The spend is expected to see Network Rail renew 650km of track.

It's part of plans, yet to be authorized by transport regulators, to keep up with 11% expected increase in demand for train travel over the next 5 years.

The publication of the Strategic Business Plan (SBP) is a major milestone in the ongoing process to determine Network Rail’s funding requirements for the five years to 2024 (Control Period 6, CP6). The plan represents Network Rail’s initial, but detailed view, following the publication of Governments (England & Wales and Scotland) high level output statements (HLOS) and statements of funds available (SoFA).

The Office of Rail and Road (ORR) will now review the plan and make a draft determination of Network Rail’s funding needs in June, and a final determination in the autumn.

The plan for 2019-24 proposes record investment in the day-to-day running of the South East route, the busiest and most economically vital part of the UK network, which connects London and its southern and south-eastern suburbs with Kent, Surrey, Sussex and cross-Channel routes to Europe.

Our plans include:

·         Completely replacing the signalling system (which controls how and where trains run) over a significant area. This includes London Victoria station and the Brighton Main Line as far as Balham, the Chatham Main line to Penge East through Brixton and Herne Hill and suburban routes to Denmark Hill and Crofton Park.

·         Rolling out digital Traffic Management technology across the whole route, providing our signallers and controllers with a system-wide view and the ability to predict delays before they happen and plan accordingly

·         Refurbishing and renewing 650km of track

·         Replacing 754 sets of points, which allow trains to move from one track to another

·         Targeted improvements to 300 earthworks – 30 per cent of the route’s total

All of the above will be targeted at areas that will have the biggest impact on train reliability and  passengers.

John Halsall, Network Rail’s South East route managing director, said: “The growth we’ve seen in recent years, and which is set to continue, show just how important the railway is – but it also means that disruption can have a major impact on many people’s lives and businesses.

 “This five-year plan represents a significant investment railway for passengers in the South East, to give them the service they expect and deserve – a more frequent, more reliable train service, supported by digital technology, on a network that is even safer for our workforce, passengers and the wider public.”

More than 510 million journeys a year are taken on South East route – far more than any other part of the network and around a third of the UK total – and that number is set to rise by a further 11% over the next five years with the new high-frequency Thameslink timetable delivering up to 24 trains per hour through central London and continued growth in jobs and housing in the South East. Freight traffic is also expected to increase – on top of the 23% growth since 2014 – driven by the booming construction industry and wider economic growth.

The investment set out today will be used to operate, maintain and renew our infrastructure, including 2,000 miles of track, 3,000 bridges, 85 tunnels and more than 500 level crossings while rolling out digital technology at our state-of-the-art rail operating centre at Three Bridges to help improve punctuality and reduce delays when incidents occur.

More from Brighton News

Weather

  • Thu

    20°C

  • Fri

    18°C

  • Sat

    24°C

  • Sun

    25°C

  • Mon

    25°C

Featured

Win With Juice

Recently Played

Traffic

  • A23 London Road - Brighton, East Sussex

    Heavy traffic on A23 London Road Northbound before A270 Viaduct Road (Preston Circus). Travel time is five minutes.

  • Warren Road - Woodingdean, East Sussex

    Very slow traffic on Warren Road Eastbound from Whitehawk to Falmer Road (The centre of Woodingdean). Travel time is four minutes.

  • A259 Brighton Road - Shoreham, West Sussex

    Very slow traffic on A259 Brighton Road Eastbound from South Lancing to A283 Old Shoreham Road (The Bridge Inn roundabout). Travel time is nine minutes.